Wrapping INK up for the Holidays!
December 19, 2017
A huge milestone moment is occurring at INK!
Windows were delivered last week and the team has officially begun installing them. Check out this picture of floor two on the north side. ‘Orange’ you glad for the close-up view?
Windows are an important milestone (especially in the winter) because once the exterior is sealed the floor can be heated! That means the team can begin steel stud framing the units without freezing their fingers.
Moving on up the building, rebar is currently being loaded up on the 12th floor in preparation to pour concrete. That means there are only two floors and a roof next to go!
More to come in 2018!